Infrastructure|11.09.2024

Mega Charger has arrived in Altishofen and is in operation

On June 4, 2024, the time had finally come: the long-awaited mega charger and battery storage unit from Designwerk arrived at the company premises of Galliker Transport AG in Altishofen. The impressive 25-tonne device, filled with state-of-the-art technology and innovation, not only brought with it an impressive 960 kWh battery capacity, but also promises to enable fast charging of up to 1 MW in the future.

Mega Charger has arrived in Altishofen and is in o...

The transportation and installation of this technically demanding battery storage system were correspondingly challenging, but extensive test runs began in the weeks following delivery. The charging capacity was increased step by step in order to finally supply the two CCS plugs with 400 kW charging capacity each. At the same time, the integration of the battery capacity into the northern area network is being driven forward.

The ceremonial handover of the Mega Charger took place on July 3, 2024 as part of the Innovation Day. Since then, countless additional tests have been carried out to continuously optimize the system. This pioneering work requires patience and precision, but Galliker is proud to be part of such a groundbreaking and sustainable project. This progress is another significant step towards CO2-free, green logistics solutions.

More articles

Mega Charger has arrived in Altishofen and is in o...
Mobility|10.12.2024

Over 13,000 Renault Group vehicles delivered CO₂-neutral every year

Renault Group Switzerland and Galliker Transport AG, Altishofen, are further expanding their zero-emission vehicle delivery capacities. Five e-car transporters from Galliker Green Logistics are currently delivering for the Renault Group, with a sixth car transporter starting operations in December. This means that a total of more than 13,000 vehicles can be delivered CO₂-neutral to Renault, Dacia and Alpine dealers in Switzerland every year.

Learn more
Mega Charger has arrived in Altishofen and is in o...
Infrastructure|06.12.2024

Public participation for the energy ecosystem

Galliker Transport, Emmi, Linde Gas Switzerland and CKW are planning an ecosystem of renewable energies in Dagmersellen that is unique in Switzerland. Numerous details of the zoning plan amendment project have now been clarified, a planning report has been drawn up and the preliminary review by the cantonal authorities is underway. Shortly before the start of the public consultation, the municipality and the project partners informed the population.

Learn more
Mega Charger has arrived in Altishofen and is in o...
Infrastructure|21.10.2024

Borner supplies new transformer buildings and electrical distribution boxes

Borner supplied some of the new transformer buildings and electrical distribution boxes that were needed on our Galliker sites for the expansion of the e-mobility infrastructure. These high-quality and robust components are essential pieces of the puzzle for the electrification of our trucks.